Storage on the construction site

Piles should be stored on blockages on sufficiently stable substrate, or directly on the surface if it is sufficiently load bearing. In case of surfaces with insufficient carrying capacity, you should install dragline bearings or other bearing surfaces.


When stacking these piles, place the underpinnings right above each other. When stacking the piles on more than two underpinnings, the underpinning also need to be right above each other. The outer underpinnings may in this case not be further inward than indicated by the black mark points. Prerequisite for this manner of storage is that the substrate cannot and should not sink or slide.


All piles are provided with two black mark points arranged for indicating the transport / storage points.

In case of transport on the construction site, damages can occur through improper and rough handling of the piles. We accept no responsibility for this.